Progress Report - Concrete Footings + Foundations

R+M Concrete are nearing the end of their work building the concrete footings and foundation walls. Today's progress photos show sections of wall covered in blankets. These walls were poured on Tuesday and once the intial concrete strength test is completed, forms will be removed and blankets reinstated until design strength is achieved.


We expect to complete the Concrete by mid-November.